In short

A pre-shipment inspection checks finished goods against drawings, specifications and packing requirements before they leave the factory. For series production, AQL sampling (ISO 2859-1) decides how many units to check and how many defects are acceptable. Its cost is small compared with the value of a rejected container.

A pre-shipment inspection (PSI) is the last check before goods leave the manufacturer. It takes place when production is complete, or nearly complete and largely packed, and verifies that what is about to be loaded matches the order, the drawings and the approved sample. For buyers sourcing from abroad, it is the final opportunity to catch problems while they are still on the factory side of the border.

What a pre-shipment inspection covers

The scope should be agreed in advance and written into an inspection checklist. For industrial components, a typical PSI covers:

  • Quantity: correct number of pieces, sets and spare parts according to the order and packing list.
  • Dimensions: measurement of critical and key dimensions against the current drawing revision.
  • Visual quality: welds, surface finish, coating, burrs, damage and cleanliness, compared with the golden sample where one exists.
  • Function and fit: assembly checks, thread gauges, moving parts, and leak or pressure test records where specified.
  • Coating: dry film thickness and, where specified, adhesion.
  • Marking and labelling: part numbers, heat numbers, nameplates or CE marking where required.
  • Documentation: material certificates, test and NDT reports, declarations of conformity and records from earlier inspection stages.
  • Packing: packing method, preservation, lifting and lashing points, and the loading plan.

For large or critical goods, loading supervision is a useful addition. It confirms that the inspected goods are the ones loaded, that they are properly secured, and that the container is sealed with a recorded seal number.

AQL sampling (ISO 2859-1) in plain words

For larger lots of identical parts, inspecting every piece is often impractical. AQL sampling gives a statistically based way to accept or reject a lot by inspecting a sample. The usual reference is ISO 2859-1, which is closely aligned with ANSI/ASQ Z1.4.

AQL stands for acceptance quality limit: the worst process average defect rate that is still considered tolerable. It is not a guarantee that a given lot contains no more than that percentage of defects. Using the standard involves three choices:

  1. Inspection level. General inspection level II is the usual default; levels I and III give smaller or larger samples, and special levels S-1 to S-4 are used when tests are destructive or expensive.
  2. Lot size. The number of units in the lot, combined with the inspection level, gives a sample size code letter and therefore the sample size.
  3. AQL per defect category. Many buyers define critical, major and minor defects separately – for example, zero acceptance for critical defects, AQL 1.0 or 2.5 for major and 4.0 for minor.

An example: a lot of 2,000 machined brackets at general inspection level II gives code letter K, which means a sample of 125 pieces. At AQL 2.5 for major defects, the lot is accepted if 7 or fewer major defects are found and rejected at 8 or more. The classification itself – what counts as critical, major or minor – must be agreed with the supplier before production starts.

Inspection cost vs the cost of a rejected container

An inspection is not free. Third-party inspections are usually priced per inspector-day, and depending on location, scope and travel, a single pre-shipment inspection typically costs somewhere between a few hundred and around a thousand euros. Treat these as illustrative ranges, not quotes.

Compare that with what is at stake once the container has left. A container of fabricated steel or machined components can easily represent tens of thousands of euros or more in goods value alone. If defects are discovered on arrival, the buyer may face:

  • Return freight, or local rework at the buyer's own cost.
  • Production stoppage or project delay while replacements are made and shipped.
  • Additional sorting and inspection at the destination.
  • Lengthy discussions about responsibility, particularly if payment has already been made in full.

In most cases, one avoided problem shipment pays for many inspections. The value is greater still when the PSI result is linked to payment, for example releasing the balance only after a passed inspection report.

What happens when a lot fails

A failed inspection is not the end of the order; it is the point at which correction is still affordable. Typical options are:

  1. 100% sorting by the supplier, removing defective units, followed by re-inspection.
  2. Rework of the defect, followed by re-inspection.
  3. Acceptance under concession, if the buyer agrees in writing that a deviation is acceptable for its use.
  4. Rejection and remanufacture for serious nonconformities.

Whatever the outcome, record the root cause and the supplier's corrective action, so that the same defect does not reappear in the next order.

Making pre-shipment inspection effective

A PSI works best as the final step of a planned sequence, not as the only check. Material verification and in-process inspection catch problems that are invisible once parts are painted, assembled or packed. A few practical habits make the final inspection more reliable: share the checklist with the supplier in advance, ensure measuring equipment is calibrated, inspect samples drawn at random from the whole lot rather than pieces selected by the factory, and record measured values, not just pass or fail.

How ISY Supply runs pre-shipment inspections

ISY Supply carries out pre-shipment inspections at manufacturers in Türkiye according to a checklist agreed with each client, with photos, measured values and a document review in the report. Where a client requests it, loading supervision can be added so that the inspected goods and the sealed container are clearly linked.

Frequently Asked Questions

When should a pre-shipment inspection take place?

When production is complete and most of the goods are packed – a common benchmark is at least 80% – so that the inspected lot represents what will actually be shipped.

What does AQL 2.5 mean?

It is the acceptance quality limit used to set the accept and reject numbers for a sample. For a sample of 125 pieces at AQL 2.5, the lot is accepted with up to 7 defects and rejected with 8 or more.

Is AQL sampling suitable for welded tanks or pressure vessels?

Usually not. Low-volume, high-value fabricated items are normally inspected unit by unit against an inspection and test plan rather than by statistical sampling.

Who pays for a pre-shipment inspection?

That is agreed commercially. Often the buyer pays for the first inspection, while the cost of re-inspection after a failed result is charged to the supplier.